CONSTRUCTION TECHNOLOGY OF STEEL STRUCTURE ALUMINUM CORRUGATED BOARD
1. Measure and lay off cables

1) According to the axis and elevation line on the main structure, according to the design requirements, the installation position line of the supporting skeleton should be accurately bounced onto the main structure.

2) Punch out all embedded parts and retest their dimensions.

3) Distribution error should be controlled during measurement and discharge, not error accumulation.

4) Measurement and lay-off shall be carried out under the condition that the wind is no more than grade 4. After laying out the line, it should be checked in time to ensure the verticality of curtain wall and the correctness of column position.

2. Install connectors

The connecting piece is welded and fixed with the embedded part on the main structure. When there is no embedded iron part on the main structure, the expansion bolt can be drilled on the main structure and fixed with the connecting iron part.

3. Install the skeleton

1) Fix the rust-proof column on the connector with welding or bolts according to the position of the spring line accurately. During installation, elevation and center line position should be checked at any time. For the skeleton column of exterior wall aluminum curtain wall with large area and high storey height, measuring instrument and line drop must be used to measure and correct its position to ensure that the skeleton vertical rod is straight and smooth. Column installation elevation deviation should not be greater than 3㎜, axis before and after deviation should not be greater than 2㎜, about deviation should not be greater than 3㎜; Two adjacent column elevation deviation should not be greater than 3㎜, the maximum elevation deviation of the same column should not be greater than 5㎜, two adjacent vertical distance deviation should not be greater than 2㎜.

2) the connectors and gaskets at both ends of the beam should be installed in the predetermined position of the column, and the installation should be firm, and the joints should be tight; The horizontal deviation of two adjacent beams should not be greater than 1㎜. The same level elevation deviation: when a curtain wall width is less than or equal to 35 m should not be greater than 5㎜; When a curtain wall width is greater than 35m, should not be greater than 7㎜.

4. Install aluminum plates

Measuring unreeling

According to the construction drawing with rivets or bolts aluminum plate veneer block by block fixed on the steel frame. 10 ~ 15 mm seam between plate and plate, in order to adjust the installation error. Aluminum plate installation, left and right, up and down the deviation should not be greater than 1.5㎜.

5. Handle plate seams

After cleaning the surface of the aluminum plate and frame with detergent, immediately place the sealing strip or weatherproof rubber strip in the gap between the aluminum plates, and then inject silicone weatherproof sealant and other materials. The glue injection should be full, and there can be no gaps or bubbles.

6. Handle curtain wall closing

Closing treatment can be used to cover the end of the wall and the keel part of the metal plate.

7. Handle deformation joints

The processing of deformation joints should first meet the needs of building expansion and settlement, and should also achieve decorative effect. Can often use heterosexual gold plate and neoprene belt system.

8. Clean the board

Remove the board surface adhesive paper, clean up the board.